Incomplete works

Incomplete works are items of the contracted scope that have not yet been done or finished, as distinct from defects, which are items that have been done but do not meet the required standard.

CONSTRUCTION DEFECT GLOSSARY·UPDATED OCTOBER 2026
Where the word is used

The phrase is Australian and British; a punch list in North America mixes both kinds of item under one name, which is why the distinction has to be made on the record rather than in the title of the list.

On site

At the first pre-completion walk about a third of what gets raised is incomplete rather than defective: the architrave is not missing, the painter has not finished the wall behind it. Counting those as defects against the carpenter is unfair to the carpenter and wrong in the numbers the client reads.

On the record

How IssuesId holds it

IssuesId separates them with the Type field: Defect or Incomplete Works, on the same register, so one walk produces one list and two correct counts. A trade who is issued an item that is really incomplete rather than defective can dispute it, and the re-typing stays on the record.

Asked alongside

Two questions people ask

What is the difference between incomplete works and defects?
Incomplete works have not been done yet; defects have been done wrongly. They are found on the same walk and often by the same person, but a defect count is read as a quality measure and incomplete works are a programme measure, so they are recorded with different types.
Can practical completion be certified with incomplete works?
Only minor ones that do not prevent the owner using the building, and they are listed as a condition of the certificate. Anything more than that is not practical completion, however small the list of defects.